GMI Asphalt LLC (the City’s paving contractor) continues to make progress revitalizing our neighborhood streets. Sidewalk work was completed on Stark Street and Dolphin Street this past week, and Merrimack Street sidewalks were base paved. Inclement weather has prevented the finish paving of Coral Street, Stark Street, Dolphin Street, Chandler Street, Shaw Street, Steeple View, Summer Street, Sweatt Street, Webster Place, and Merrimack Street. Due to the July 4 holiday this week, the finish paving is tentatively scheduled for the week of July 10.